浅谈220kV电缆较长距离试验方法
220kV cables of longer distances over test
JIANG Qian
(Eeat China Power Transmission & Transformation Engineering co.,Putuo District,Shanghai,china)
ABSTRACT:In recent years, with the rapid development of urban power grid construction, high voltage cable has been widely used, this paper combined with 220kV East Green Change - traction cable line project, the cable from the long, cross-section of more interconnected, according to the cable transfer of test specification, the actual situation of the construction site, a detailed description of the 220kV cable pilot projects over test timing, the choice of test equipment and test methods development; test security measures.
KEY WORDS: Over test of 220kV cables;test time ;test equipment; test methods ; safety measures
摘要:近年来,随着城市电网建设的飞速发展,超高电压等级的电缆也被广泛使用,本文主要结合220kV东青变-牵引变电缆线路工程,电缆距离较长,交叉互联段较多,根据电缆交接试验规范规定、施工现场的实际情况,详细的介绍了220kV电缆交接试验的试验项目时间的安排、试验仪器设备的选择及试验方法的制定;试验的安全措施。
关键字:220kV电缆交接试验 试验时间 试验仪器设备 试验方法 安全措施
0引言
220kV东青~常州牵引站工程为沪宁城际高铁重要配套供电项目,线路分别始于220kV东青变电站北起#1构架、#16构架,止于常州牵引站东起#1构架、#2构架。全线双回路电缆路径5.7公里,电缆型号为ZR-YJLW03-127/220-1*1600。YJLW03 1×1600mm2,电缆敷设方式为电缆沟、箱涵、桥架、顶管通道敷设,由于工期短,任务重,电缆敷设、接头施工完毕后,送点节点只剩7天时间,电缆试验合格与否直接关系到验收送电时间,所以合理安排试验时间,选择便于操作、满足试验要求的试验仪器及设备,制定详细的试验方案,尤为关键。根据交接试验规范,220kV电缆试验项目如下:
1.电缆核相试验;
2.耐压试验前后测量绝缘电阻;
3.测量金属屏蔽层电阻和导体电阻比;
4.电力电缆线路交叉互联系统试验;
4.1交叉互联系统的对地绝缘的直流耐压试验;
4.2护层过电压保护器试验;
4.3互联箱试验;
5.电缆接地电阻测试;
6.电缆主绝缘交流耐压试验;
7.工频线路参数试验测量;。
7.1.测量电缆线路正序阻抗。
7.2.测量电缆线路零序阻抗。
7.3测量电缆线路正序电容
1.试验日期和试验地点的合理安排:
试验项目 计划试验时间 计划试验地点
1.电缆核相试验 2010年3月16日 220kV牵引变电所
2.耐压试验前后测量绝缘电阻 2010年3月16日 220kV东青变电所
3.测量金属屏蔽层电阻和导体电阻比 2010年3月16日 220kV牵引变电所